07/08/2026
LA CASTELLANA KKB CDD SUB-PROJECT STATUS UPDATE
As of the latest monitoring, the La Castellana KKB CDD sub-projects continue to make steady progress. The Hanging Bridge Project in Barangay Robles has reached a 42.671% physical accomplishment. Meanwhile, the One-Unit, Two-Classroom School Building with Amenities in Barangay Sag-ang has achieved a 77.41% physical accomplishment, making it the most advanced among the ongoing sub-projects. In addition, the Purchase and Installation of the Public Address System in Barangay Cabagna-an has attained a 50.00% physical accomplishment. These accomplishments reflect the continued implementation and progress of the municipality's KKB CDD sub-projects toward their successful completion.
Note: The actual accomplishment percentage is based solely on the installed project components. Material fabrication and on-site delivery are not included in the accomplishment calculation.